2016 Bond Update

In May, 2016 Comstock voters approved a $40,130,000 bond issue.  These dollars will be spent in three series over the course of nine years to provide for improvements and preservation of our schools. By issuing the bonds in three series, the overall interest costs are less than if the bonds were issued all at one time.

This web page has been set up so that Comstock voters can see what projects are involved for each series, and so that we can share updates on the progress of these various projects. 

Series 1

$8,000,000
2016-17

Series One of our bond improvements include technology updates, secure entries, and more. 
Learn more...

Series 2

$15,975,000
2019

The second series of our improvements will come when our second bond is disbursed in 2019. These projects include... . 
Learn more...

Series 3

$16,155,000
2022

Our third series begins in 2022, and will include major renovations at Comstock High School. 
Learn more...